Skip To Main Content

Schools & Programs

Project Updates

Information from the Superintendent’s Report Presented During the February 9, 2026 Board Meeting

 

MR. JEFF SMITH, DIRECTOR OF FACILITIES & MAINTENANCE

MR. TONY SOLES, CAPITAL PROJECTS FACILITATOR 

Facilities Projects Update

WINDSOR HILL ART INFUSED ELEMENTARY SCHOOL

ROOFING AND EXTERIOR WALLS

  • Final punch list in progress
  • FUNDING SOURCE – REFERENDUM

HVAC Replacement

  • Replacement complete
  • Waiting on correct heat strips for Media Center
  • FUNDING SOURCE – 8% Funds

SUMMERVILLE HIGH SCHOOL

Tennis Courts

  • Design in progress for AMS location

  • FUNDING SOURCE – TIF and 8% Funds

GREGG MIDDLE SCHOOL

Gym Floor Resurfacing

  • Touch-ups scheduled for Spring Break
  • FUNDING SOURCE – 8% Funds

NES/BHES – PLAYGROUND RENOVATIONS

  • Installation complete
  • FUNDING SOURCE – 8% Funds

CURRENT & UPCOMING BIDS & PROJECTS

  • AMS Roofing – Anticipated start 2/23/2026
  • AMS Restroom Renovations – Kickoff meeting 2/11/2026
  • GMS Roofing/Exterior Envelope – Project out for bid late February
  • Asphalt Contract – February 2026
  • NES Ceiling grid/lighting/Ductwork/ Abatement project – February / March 2026 bid time frame

 

Behind the Scenes  of Sand Hill Elementary Addition Project

Presented by GF

 

Referendum Project Updates

ELEMENTARY SCHOOL AT THE PONDS

  • Continuing efforts for land agreement

SUMMERVILLE ELEMENTARY ADDITION 

  • Structural block on the second floor is nearing completion

  • Structural steel for the roof will begin on 2/16/26

  • Above ceiling Mechanical, Electrical and Plumbing (MEP) rough-in is progressing on the first floor

  • In-wall MEP is in progress throughout the building

Summerville High School

Gym

  • Fire and Egress Modeling and Analysis in progress – Results are scheduled to be completed this week

  • Construction Documents scheduled for submittal 6/1/2026

ASHLEY RIDGE HIGH ADDITIONS and RENOVATIONS

  • New Band room Block is nearing completion

  • In-Wall MEP rough-ins are being installed

  • Scheduled Completion Date Band Room May 25, 2026

  • Demo at the new Weight Room is nearing completion

  • New Weight Room scheduled completion date is 6/1/26

Fort Dorchester High School

Classroom Addition

  • Permitting is complete
  • Pre-Qualified Contractors will submit bids on 2/17/2026

KNIGHTSVILLE ELEMENTARY SCHOOL CAMPUS UPGRADES

  • Kick-Off meeting was held on 1/29/2026

  • Programming and conceptual design in progress

OTHER CIP CONSTRUCTION

OAKBROOK MIDDLE SCHOOL

ADDITION

  • Awaiting LLR final approval of Fire Riser drawing 
  • TIF funds

OAKBROOK ELEMENTARY SCHOOL

ADDITION

  • Roofing is complete
  • Mechanical, Electrical, Plumbing (MEP) in progress
  • Permanent power turned on this week
  • Above ceiling inspection is tentatively scheduled for 3/2/2026
  • TIF funds

BUS MAINTENANCE FACILITY@ OAKBROOK DEPOT

  • Pre-construction meeting tentatively scheduled for 2/16/26
  • Working with the GC and design firm to coordinate construction
  • General Fund (approved 2023)