2024 Referendum Master Project List

 

View construction and improvement projects funded by the 2024 Referendum, including funding source, project summaries, and estimated completion timelines.

 

Last Updated - October 27 , 2026

2024 Referendum Budget

Your 2024 Referendum Dollars at Work

Safety and Security

SES Classroom Addition

Roof Replacements

Parking & Traffic Improvements

Sand Hill Elementary Classroom Addition

Ashley Ridge Classroom Additions & Renovations

Search for School

Filter By School Level

Alston Middle School - Ceiling Grid, Tile and Lighting Replacements

Project Summary

  • Funding Source - 2024 Referendum
  • Status - On Hold
    • Design approved by OSF
    • Project on hold due to change in scope of work.
  • Estimated Completion Date: TBD

Campus Facts

  • Built in 1953
  • Upgrades in: 1990, 2001, 2016

 

  • 2024 Referendum
  • In Progress
Alston Middle School - Interior Wall Abatement/Renovation

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 1953
  • Upgrades in: 1990,2001, 2016
  • 2024 Referendum
  • Completed
Alston Middle School - Replace Interior Doors and Frames

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed 7/31/2026

 

Campus Facts

  • Built in 1953
  • Upgrades in: 1990, 2001, 2016
  • 2024 Referendum
  • Completed
Alston Middle School - Restroom Renovations

Project Summary

  • Funding Source - 2024 Referendum
  • Status: Completed

Campus Facts

  • Built in 1953
  • Upgrades in: 1990, 2001, 2016

 

  • 2024 Referendum
  • Completed
Alston Middle School - Safety and Security Upgrades

Project Description

  •  Additional cameras
  • Weapons Detection
  • Radio project. Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Impact resistant film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status -  Completed

Campus Facts

  • Built in 1953
  • Upgrades in: 1990, 2001, 2016
  • 2024 Referendum
  • Completed
Alston-Bailey Elementary - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Radio project. Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Secured Vestibule
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 2016
  • 2024 Referendum
  • Completed
Ashley Ridge High School - Car Rider Loop Upgrade

Project Summary

  • Funding Source - 2024 Referendum
  • Status
    • Opened for the first day of school
    • Punch list repairs will take place during the Fall Break
    • Passed Proof-Roll on 10/21/26
    • Paving scheduled for completion 10/27/26

Campus Facts

  • Built in 2008
  • Upgrades in: 2011, 2014
  • 2024 Referendum
  • Completed
Ashley Ridge High School - Classroom Additions & Rennovations

Project Summary

  • Funding Source - 2024 Referendum
  • Status 
    • Completed

Campus Facts

  • Built in 2008
  • Upgrades in: 2011, 2014

 

  • 2024 Referendum
  • Completed
Ashley Ridge High School - Roof Replacement - Section 5 (Grade F)

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed July 2026

Campus Facts

  • Built in 2008
  • Upgrades in: 2011, 2014

 

  • 2024 Referendum
  • Completed
Ashley Ridge High School - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Weapons Detection
  • Radio project. Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 2008
  • Upgrades in: 2011, 2014

 

  • 2024 Referendum
  • Completed
Ashley Ridge High School - Wi-Fi Infrastructure Expansion

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 2008
  • Upgrades in: 2011, 2014

 

  • 2024 Referendum
  • Completed
Beech Hill Elementary - Ceiling Grid, Tile, and Lighting Replacement

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed 7/27/2026

Campus Facts

  • Built in 1992
  • Upgrades in: 1992, 1997
  • 2024 Referendum
  • Completed
Beech Hill Elementary - Roof Replacement -Section 1 (Grade F)

Project Summary

  • Funding Source - 2024 Referendum
  • Status. 
    • Punch list in  progress
  • Estimated Completion Date: August 2026

Campus Facts

  • Built in 1992
  • Upgrades in: 1992, 1997
  • 2024 Referendum
  • In Progress
Beech Hill Elementary - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Radio project. Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Secured Vestibule
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 1992
  • Upgrades in: 1992, 1997
  • 2024 Referendum
  • Completed
Dubose Middle School - Replace Concrete and Improve Drainage in Courtyard

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 1985
  • 2024 Referendum
  • Completed
Dubose Middle School - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Weapons Detection
  • Radio project. Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Impact resistant film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 1985
  • 2024 Referendum
  • Completed
Dubose Middle School - Student Restroom Renovations

Project Summary

  • Funding Source - 2024 Referendum
  • Status
    • Design in Progress
  • Estimated Completion Date: Summer 2027

Campus Facts

  • Built in 1985
  • 2024 Referendum
  • Planning
Eagle Nest Elementary - Exterior Wall Renovation/ Windows

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Bid Awarded
  • Estimated Completion Date: Summer 2027

Campus Facts

  • Built in 2007
  • Upgrades in: 2016
  • 2024 Referendum
  • In Progress
Eagle Nest Elementary - Roof Replacement -Section 1 (Grade F)

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Bid Awarded
  • Estimated Completion Date: Summer 2027

Campus Facts

  • Built in 2007
  • Upgrades in: 2016
  • 2024 Referendum
  • In Progress
Eagle Nest Elementary - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Radio project. Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 2007
  • Upgrades in: 2016
  • 2024 Referendum
  • Completed
East Edisto Middle School - Additional Parking

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 2022

 

  • 2024 Referendum
  • Completed
East Edisto Middle School- Safety and Security Upgrades

Project Description

  • Additional cameras
  • Weapons Detection
  • Radio project. Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 2022

 

  • 2024 Referendum
  • Completed
Elementary School - New School (Ponds)

Project Summary

  • Funding Source - 2024 Referendum
  • Status
    • Awaiting property conveyance
    • The developer has submitted final plat for approval                                          
  • Estimated Completion Date: TBD
  • 2024 Referendum
Elementary School - New School (Yerby Tract)

Project Summary

  • Funding Source - 2024 Referendum
  • Status
    • Board approved reallocation of funds at November 10, 2025 meeting.
  • Estimated Completion Date: TBD

 

  • 2024 Referendum
Eugene Sires Elementary - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Radio project. Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 2016
  • 2024 Referendum
  • Completed
Flowertown & Newington Elementary - Bus/Car Rider Loop Reconfiguration

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

Flowertown Elementary

  • Built in 1977
  • Upgrades in: 1981, 1989, 2016

Newington Elementary

  • Built in 1975
  • Upgrades in: 1989, 2000, 2016
  • 2024 Referendum
  • Completed
Flowertown & Newington Elementary - Ceiling Grid, Tile and Lighting Replacement

Project Details

  • NES will be performed in 2 phases.
  • FES to begin after NES  is complete.

Project Summary

  • Funding Source - 2024 Referendum
  • Status 
    • Received OSF approval and project will be put out for bid
    • NES Phase 1 - NES Phase 1 completed July 2027

Campus Facts

Flowertown Elementary

  • Built in 1977
  • Upgrades in: 1981, 1989, 2016

Newington Elementary

  • Built in 1975
  • Upgrades in: 1989, 2000, 2016
  • 2024 Referendum
  • In Progress
Flowertown & Newington Elementary - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Radio project. Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Secured Vestibule
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

Flowertown Elementary

  • Built in 1977
  • Upgrades in: 1981, 1989, 2016

Newington Elementary

  • Built in 1975
  • Upgrades in: 1989, 2000, 2016
  • 2024 Referendum
  • Completed
Flowertown & Newington Elementary - Transite Panel Abatement & Replacement Phase 1

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed 
    • Phase 1 (pods & hallways) Complete

Campus Facts

Flowertown Elementary

  • Built in 1977
  • Upgrades in: 1981, 1989, 2016

Newington Elementary

  • Built in 1975
  • Upgrades in: 1989, 2000, 2016
  • 2024 Referendum
  • Completed
Flowertown & Newington Elementary - Transite Panel Abatement & Replacement Phase 2

Project Details

  • FES & NES Phase 1 (pods & hallways) Complete;
  • Phase 2 (classrooms) are currently out for bid for NES.  
  • FES to begin after NES complete.

Project Summary

  • Funding Source - 2024 Referendum
  • Status 
    • Phase 2 (classrooms) to begin Summer 2026
  • Estimated Completion Date: Coinciding with Ceiling Grid, Tile and Lighting Replacement project

Campus Facts

Flowertown Elementary

  • Built in 1977
  • Upgrades in: 1981, 1989, 2016

Newington Elementary

  • Built in 1975
  • Upgrades in: 1989, 2000, 2016
  • 2024 Referendum
  • In Progress
Fort Dorchester Elementary - Exterior Wall Renovation

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Bid awarded
  • Estimated Completion Date: Summer 2027

Campus Facts

  • Built in 2002
  • 2024 Referendum
  • In Progress
Fort Dorchester Elementary - Gutter Replacements-Sections 1-7

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Design in progress
  • Estimated Completion Date: Summer 2027

Campus Facts

  • Built in 2002
  • 2024 Referendum
  • Planning
Fort Dorchester Elementary - Roof Replacements - Sections 1, 3 (Grade F)

Project Summary

  • Funding Source - 2024 Referendum
  • Status -Bid awarded
  • Estimated Completion Date: Summer 2027

Campus Facts

  • Built in 2002
  • 2024 Referendum
  • In Progress
Fort Dorchester Elementary - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Radio project. Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Secured Vestibule
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 2002
  • 2024 Referendum
  • Completed
Fort Dorchester High School - Classroom & lighting renovations

Project Summary

  • Preconstruction meeting held 9/22/2026
  • Construction to begin 10/22/2026
  • Spring 2027 anticipated completion

Campus Facts

  • Built in 1991
  • Upgrades in 1998, 2000, 2001, 2011, 2024

 

  • 2024 Referendum
  • Planning
Fort Dorchester High School - Classroom Addition

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Mobilization to start this week to start week of 10/25/26 

Campus Facts

  • Built in 1991
  • Upgrades in 1998, 2000, 2001, 2011, 2024

 

  • 2024 Referendum
  • In Progress
Fort Dorchester High School - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Weapons Detection
  • Radio project. Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 1991
  • Upgrades in 1998, 2000, 2001, 2011, 2024

 

  • 2024 Referendum
  • Completed
Gregg Middle School - Exterior Wall Renovation

Project Summary

  • Funding Source - 2024 Referendum
  • Status
    • Design complete
    • Contract awarded.
    • Pre-construction meeting scheduled 5/6/26
  • Estimated completion: August 2026

Campus Facts

  • Built in 1973
  • Upgrades in: 1998

 

  • 2024 Referendum
  • In Progress
Gregg Middle School - Roof Replacements - Sections 1-6 (Grade F)

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 1973
  • Upgrades in: 1998

 

  • 2024 Referendum
  • Completed
Gregg Middle School - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Weapons Detection
  • Radio project.  Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 1973
  • Upgrades in: 1998
  • 2024 Referendum
  • Completed
Joseph Pye Elementary - Exterior Wall Renovation

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Bid awarded
  • Estimated Completion Date: Summer 2027

Campus Facts

  • Built in 2011
  • 2024 Referendum
  • In Progress
Joseph Pye Elementary - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Radio project. Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Secured Vestibule
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 2011
  • 2024 Referendum
  • Completed
Knightsville Elementary - Abatement, Repaint & Refloor Buildings and Classrooms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 1948
  • Upgrades in: 1966, 1991, 1997, 2001
  • 2024 Referendum
  • Completed
Knightsville Elementary - Additions and Renovations

Project Summary

  • Funding Source - 2024 Referendum. Funded out of the reallocation of Yerby funds.
  • Status
    • Demolition is underway
    • Continuing utility locates and site prep
    • Permitting in progress
    • Final Construction Documents sent to OSF on10/16/26
    • Estimated Completion Date - 12/31/2028

Campus Facts

  • Built in 1948
  • Upgrades in: 1966, 1991, 1997, 2001
  • 2024 Referendum
  • In Progress
Knightsville Elementary - Exterior Wall Renovation

Project Summary

  • Funding Source - 2024 Referendum
  • Status: Contract awarded to vendor. Project on hold due to campus upgrade per Board approval.
  • Estimated Completion time: NA 

Campus Facts

  • Built in 1948
  • Upgrades in: 1966, 1991, 1997, 2001
  • 2024 Referendum
  • Planning
Knightsville Elementary - Roof Replacement - Section 1 (Grade F)

Project Summary

  • Funding Source - 2024 Referendum
  • Status: Contract awarded to vendor. Project on hold due to campus upgrade per Board approval.
  • Estimated Completion Date: NA

Campus Facts

  • Built in 1948
  • Upgrades in: 1966, 1991, 1997, 2001
  • 2024 Referendum
  • Planning
Knightsville Elementary - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Radio project. Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 1948
  • Upgrades in: 1966, 1991, 1997, 2001
  • 2024 Referendum
  • Completed
Oakbrook Elementary - Exterior Wall Renovation

Project Summary

  • Funding Source - 2024 Referendum
  • Status
    • Completed May 2026

Campus Facts

  • Built in 1985
  • Upgrades in: 1997, 2026
  • 2024 Referendum
  • Completed
Oakbrook Elementary - Repave Parking Lot

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 1985
  • Upgrades in: 1997, 2026
  • 2024 Referendum
  • Completed
Oakbrook Elementary - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Radio project. Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Secured Vestibule
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 1985
  • Upgrades in: 1997, 2026
  • 2024 Referendum
  • Completed
Oakbrook Middle School - Cafe Renovations

Project Summary

  • Funding Source - 2024 Referendum
  • Status
    • Design complete
  • Estimated Completion Date: Summer 2026

Campus Facts

  • Built in 1985
  • Upgrades in: 2025

 

  • 2024 Referendum
  • In Progress
Oakbrook Middle School - Exterior Wall Repairs

Project Summary

  • Funding Source - 2024 Referendum
  • Status
    • Completed May 2026

Campus Facts

  • Built in 1985
  • Upgrades in: 2025
  • 2024 Referendum
  • Completed
Oakbrook Middle School - Repave Parking Lot

Project Summary

  • Funding Source - 2024 Referendum
  • Status
    • Work on active campus is complete.  Remaining work will finish after construction is complete.
  • Estimated Completion Date: Summer 2026

Campus Facts

  • Built in 1985
  • Upgrades in: 2025

 

  • 2024 Referendum
  • In Progress
Oakbrook Middle School - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Weapons Detection
  • Radio project. Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 1985
  • Upgrades in: 2025

 

  • 2024 Referendum
  • Completed
River Oaks Middle School - Exterior Wall Renovation/ Windows

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Bid awarded
  • Estimated Completion Date - Summer 2027

Campus Facts

  • Built in 2007

 

  • 2024 Referendum
  • In Progress
River Oaks Middle School - Roof Replacements - Section 1

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Bid awarded
  • Estimated Completion Date - Summer 2027

Campus Facts

  • Built in 2007

 

  • 2024 Referendum
  • In Progress
River Oaks Middle School - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Weapons Detection
  • Radio project. Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 2007

 

  • 2024 Referendum
  • Completed
Rollings Middle School of the Arts - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Weapons Detection
  • Radio project.  Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 2017

 

  • 2024 Referendum
  • Completed
Sand Hill Elementary - New Addition - 10 Classrooms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 2016
  • Upgrades in: 1997, 2025
  • 2024 Referendum
  • Completed
Sand Hill Elementary - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Radio project. Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 2016
  • Upgrades in: 1997, 2025
  • 2024 Referendum
  • Completed
Spann Elementary - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Radio project. Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 1960
  • Upgrades in: 1962, 1991, 1998
  • 2024 Referendum
  • Completed
Summerville Elementary - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Radio project. Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 1950
  • Upgrades in: 1956, 1991, 2000, 2026
  • 2024 Referendum
  • Completed
Summerville Elementary - Wing Addition - 16 classrooms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed July 2026

Campus Facts

  • Built in 1950
  • Upgrades in: 1956, 1991, 2000, 2026
  • 2024 Referendum
  • Completed
Summerville High School - Construct New Gym & Renovate Aux Gym to Classrooms

Project Summary

  • Funding Source - 2024 Referendum
  • Status
    • Site fencing is complete
    • Site work is underway
    • Earthquake Drain installation complete
    • Underground storm water and sewer line is complete
    • Foundation work has started
  • Estimated Completion Date: Summer 2027

Campus Facts

  • Built in 1969
  • Upgrades in: 1971, 1976, 1997, 1986, 1988, 2001, 2016, 2018

 

  • 2024 Referendum
  • In Progress
Summerville High School - Paving for Parking Lot and Bus Loop

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 1969
  • Upgrades in: 1971, 1976, 1997, 1986, 1988, 2001, 2016, 2018

 

  • 2024 Referendum
  • Completed
Summerville High School - Restroom and Classroom renovations

Project Summary

  • Funding Source - 2024 Referendum
  • Status - In Progress
  • Estimated Completion Date: August 2026

Campus Facts

  • Built in 1969
  • Upgrades in: 1971, 1976, 1997, 1986, 1988, 2001, 2016, 2018

 

  • 2024 Referendum
  • In Progress
Summerville High School - Roof Replacement - Section 1 (Grade F)

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Planning
  • Estimated Completion Date: TBD

Campus Facts

  • Built in 1969
  • Upgrades in: 1971, 1976, 1997, 1986, 1988, 2001, 2016, 2018

 

  • 2024 Referendum
  • Planning
Summerville High School - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Weapons Detection
  • Radio project. Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 1969
  • Upgrades in: 1971, 1976, 1997, 1986, 1988, 2001, 2016, 2018

 

  • 2024 Referendum
  • Completed
William Reeves Elementary - Exterior Wall Renovation

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Planning
  • Estimated Completion Date: TBD

Campus Facts

  • Built in 2007
  • 2024 Referendum
  • Planning
William Reeves Elementary - Roofing Replacement- Sect. 2

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Planning
  • Estimated Completion Date: TBD

Campus Facts

  • Built in 2007
  • 2024 Referendum
  • Planning
William Reeves Elementary - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Radio project.  Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 2007
  • 2024 Referendum
  • Completed
William Reeves Elementary - William Reeves Elementary Roof Replacement- Section 1 (Grade F)

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Planning
  • Estimated Completion Date: TBD

Campus Facts

  • Built in 2007
  • 2024 Referendum
  • Planning
Windsor Hill Arts Infused Elementary - Exterior Wall Renovation

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 1990
  • Upgrades in: 1997
  • 2024 Referendum
  • Completed
Windsor Hill Arts Infused Elementary - Repave, Restripe, Repair and Replace Curb

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Requesting quote from approved vendors under new contract
  • Estimated Completion Date: TBD

Campus Facts

  • Built in 1990
  • Upgrades in: 1997
  • 2024 Referendum
  • Planning
Windsor Hill Arts Infused Elementary - Roof Replacements - Sections 1-3 (Grade F)

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 1990
  • Upgrades in: 1997
  • 2024 Referendum
  • Completed
Windsor Hill Arts Infused Elementary - Safety and Security Upgrades

Project Description

  • Additional cameras
  • Radio project. Allows schools to communicate with:
    • First Responders
    • District Office
    • Other Schools
  • Impact resistant window film
  • Door alarms

Project Summary

  • Funding Source - 2024 Referendum
  • Status - Completed

Campus Facts

  • Built in 1990
  • Upgrades in: 1997
  • 2024 Referendum
  • Completed